Lake Water to Cool Supercomputers at CSCS

Tuesday, November 15th, 2011

High-performance computing centres use a great deal of electricity. In order to run its new computer centre in Lugano-Cornaredo as energy-efficiently and cost-effectively as possible, CSCS is using the natural resource of Lake Lugano to cool its supercomputers and the new building.

A high-performance computing centre like the CSCS (Swiss National Supercomputing Centre) uses as much electricity every day as a small town. About a third of this electricity is used for cooling. If supercomputers are not constantly cooled, they overheat and, in the worst case scenario, may be damaged.

Three pumps move up to 760 litres of water per second
In conventional computing centres, compressors generate cold water to cool the computers. To save energy, CSCS will make use of a natural cooling resource: water extracted from Lake Lugano at 45 meters depth at a temperature of 6 degrees Celsius. This will greatly reduce the amount of electricity used by CSCS for cooling.

To operate the cooling system, a pumping station has been built on the lake shore in Parco Ciani, in the centre of Lugano. This is connected by a pipe to the 13 tonne, six metre high suction baskets which have been immersed at a depth of over forty metres. Through this pipe, three pumps in the pumping station will pump up to 760 litres of water per second. 460 litres will go to CSCS for cooling purposes, while up to 300 litres will be available to AIL for its water reservoir, which has yet to be built. On its way to CSCS, the water will climb 30 metres and cover a distance of 2.8 kilometres.

n the labyrinth of the pumping station: five metres beneath the lawns of Parco Ciani, over 700 litres of water per second are pumped out of Lake Lugano. (Picture: CSCS)

High-tech underground control centre
A steel ladder leads down to the high-tech underground control centre of the pumping station. The electrical infrastructure has been installed on steel mesh platforms about 2.5 metres above the ground, underneath this – covering a surface area of about 200 square metres –are the three pumps, a further backup pump, and two shock absorbing containers which will protect the pipeline from damage in the event of a sudden pressure surge.

On two sides of the pumping station, two massive pipes pierce the metre-thick walls. The pipeline connecting CSCS to the pumping station is 80 centimetres in diameter. On its way to CSCS, the water´s temperature will increase by up to 0.5°C. At the arrival point at CSCS, the lake water circuit and the internal cooling water circuit meet in man-sized heat exchangers. The internal water cooling circuit delivers the water, which has now reached 8 -9°C, to the supercomputers for cooling.

The suction strainers for the lake water pipe, just before they were lowered 45 metres into Lake Lugano. (Picture: CSCS)

One pumping operation for double the cooling effect
Once the water has passed through this first cooling circuit, it has been heated up by eight degrees. The now 16 to 17 °C is sent through a further heat exchanger, connected to a second cooling circuit. This mid-temperature circuit cools the air in the housings for the computers and hard drives of lesser energy density, that can therefore be cooled with water that is less cold. This means that with one pumping operation, two cooling is supplied to two circuits to cool two types of system.

The cold water pipe is designed to cool supercomputers of up to 14 megawatts on the first cooling circuit. The second circuit can cool  a further seven megawatts of computers. The more the second circuit is used, the higher the waste heat absorbed by the water and so the more useful it is to the local industrial works who will be able to use it.

Before the lake water returns to the lake, it passes through a stilling basin which can hold 120 cubic metres. The basin collects the water and makes sure that it flows freely down the return pipe back to the lake at a constant pressure and with no need for further power to be used. On the contrary, the plan is to use the energy generated as it falls to produce electricity. That is why connections for a microturbine have been provided in the pumping station.

So as not to affect the ecological balance of the lake, the water going back into the lake must never exceed 25 degrees Celsius. To ensure that this is always the case, a back-mixing funnel has been fitted which will add cold water if necessary.

(Article by Simone Ulmer, CSCS)

Additional reading: CSCS Media Release »

“Roofing Ceremony” for the new Swiss National Supercomputing Centre

Friday, February 4th, 2011

On February 3rd, 2011 ETH Zurich and Implenia Impresa Generale SA are pleased to celebrate with the authorities the “Roofing Ceremony” for the new Swiss Supercomputing Centre in Lugano. This is a party that is traditionally thrown for the workers to celebrate reaching and completing the roof of a new construction. A successful roofing ceremony is meant to bring good fortune to the new building. It was hence a great pleasure to see nearly 300 workers turn up for this event and thoroughly enjoy themselves.

The construction project started in January, 2010 with the demolition of an old building (previous bus terminal) and the excavation work. The construction of the building shell started in August 2010 and finished on February 3, 2011 with a “roofing ceremony”.

As a special thanks to the workers CSCS produced a video showing the achievements reached so far.

YouTube Preview Image

Additional movie formats (Quicktime) »

The new data center offers 8’000 m2 for technical installation (2’000 m2 for the supercomputers) and 3’000 m2 for offices. The construction will continue in the next months with the interior work and the completion of the building front.

The new centre will be operative at the beginning of 2012.

New CSCS Building: Assembling the Data Centre Roof

Wednesday, December 22nd, 2010

Have a look to the assembling of the data center roof for the new Swiss National Supercomputing Centre (CSCS) in Lugano.

In the movie (see here below) you can see the positioning of the roof beams for the new machine room. Each roof beam is 35 meters long and weights 50 tons.The machine room will offer a surface of about 2’000 square meters without pillars to host the supercomputers.

The mobile crane used is the largest worldwide and can lift up to 1200 tons. The crane itself weights about 380 tons.

YouTube Preview Image

Click here for different video formats (Quicktime) and additional videos on CSCS.

Have a view to the webcam or the home page of the construction project.

Construction of the New CSCS Building Proceeds at Fast Pace

Monday, December 6th, 2010

Construction of the new CSCS building proceeds at fast pace. The shell is almost complete, the roof being built these days.

The new data center will house the next generation of supercomputers, it covers an area of 2000 square meters and is void of pillars, allowing more freedom in placing the latest models of supercomputers.

The roof is currently being built using the strongest mobile crane on the market, featuring a telescoping beam that extends from 20 to 100 meters and can lift weights up to 1200 tons. Each of the eight beam weighs 50 tons and is 35 m long.

The next photo shows the future machine room.

The administrative building with in foreground the crane that will be used to mount the roof.

Check the web pages of the construction project about the latest news or have a view of the webcams placed at the construction site.

Laying the Foundation Stone for CSCS Building in Lugano

Monday, October 18th, 2010

Monday, October 18 has been an important day for  the implementation of the Swiss National HPC Initiative (HPCN).  In Lugano Cornaredo there was the ceremony for the laying of the foundation stone for the new CSCS building. The ceremony has been attended by representatives of ETH Zurich, the Canton of Ticino, the City of Lugano, Implenia (the construction contractor) together with a lot of other guests.

Raffaele Balmelli, head of Implenia Ticino, Thomas Schultess, Director CSCS and Roman Boutellier Vice President Personal and Ressources of ETH Zurich during the foundation stone ceremony on the construction site.

Handshake between Raffaele Balmelli (Implenia) and Roman Boutellier (ETH Zurich).

The total investment for the new building will be about 80 millions CHF. The new center is needed to host the future national supercomputer with a computing capacity of some petaflops and a power consumption of up to 5 Megawatt (the existing building in Manno is limited to less than to 2 Megawatt). Special attention has been put to reducing the energy consumption of the whole center. The offices will be build according to the Minergie standard and the supercomputer will be cooled using water from the lake of Lugano. The excess heat will be made available to the city of Lugano.

The new building in Lugano should be ready by the end of 2011 and the relocation from Manno to Lugano ought to be done by mid 2012.

Read also the article on ETH Life »